A decision making method for congested transmission lines of KEPCO system

Jun Min Cha, Kwang Hae Oh, Byong Jun Lee, Kil Yeong Song

Research output: Chapter in Book/Report/Conference proceedingConference contribution

3 Citations (Scopus)

Abstract

In this paper, fuzzy theory is used to quantify some subjective criteria to consider uncertain factors for transmission line reinforcement planning. As it can be easily applied to multi attribute decision making problems such as power system planning, Sugeno's fuzzy integral is also used in the proposed method. To verify the proposed algorithm, some bottle-neck lines are searched for the case that the amount of Maximal Load Supplying Capability(MLSC) is small using the results of contingency analysis for Korea Electric Power Corporation(KEPCO)'s 345 kV transmission line in 1998. And several feasible alternatives are composed for line reinforcement which can solve the bottle-neck problem in KEPCO system.

Original languageEnglish
Title of host publicationPowerCon 2000 - 2000 International Conference on Power System Technology, Proceedings
PublisherInstitute of Electrical and Electronics Engineers Inc.
Pages1425-1429
Number of pages5
Volume3
ISBN (Print)0780363388, 9780780363380
DOIs
Publication statusPublished - 2000
EventInternational Conference on Power System Technology, PowerCon 2000 - Perth, Australia
Duration: 2000 Dec 42000 Dec 7

Other

OtherInternational Conference on Power System Technology, PowerCon 2000
CountryAustralia
CityPerth
Period00/12/400/12/7

Fingerprint

Bottles
Electric lines
Reinforcement
Decision making
Planning
Industry

Keywords

  • Decision making
  • Sugeno's fuzzy integral
  • Transmission line reinforcement planning

ASJC Scopus subject areas

  • Energy Engineering and Power Technology
  • Electrical and Electronic Engineering

Cite this

Cha, J. M., Oh, K. H., Lee, B. J., & Song, K. Y. (2000). A decision making method for congested transmission lines of KEPCO system. In PowerCon 2000 - 2000 International Conference on Power System Technology, Proceedings (Vol. 3, pp. 1425-1429). [898178] Institute of Electrical and Electronics Engineers Inc.. https://doi.org/10.1109/ICPST.2000.898178

A decision making method for congested transmission lines of KEPCO system. / Cha, Jun Min; Oh, Kwang Hae; Lee, Byong Jun; Song, Kil Yeong.

PowerCon 2000 - 2000 International Conference on Power System Technology, Proceedings. Vol. 3 Institute of Electrical and Electronics Engineers Inc., 2000. p. 1425-1429 898178.

Research output: Chapter in Book/Report/Conference proceedingConference contribution

Cha, JM, Oh, KH, Lee, BJ & Song, KY 2000, A decision making method for congested transmission lines of KEPCO system. in PowerCon 2000 - 2000 International Conference on Power System Technology, Proceedings. vol. 3, 898178, Institute of Electrical and Electronics Engineers Inc., pp. 1425-1429, International Conference on Power System Technology, PowerCon 2000, Perth, Australia, 00/12/4. https://doi.org/10.1109/ICPST.2000.898178
Cha JM, Oh KH, Lee BJ, Song KY. A decision making method for congested transmission lines of KEPCO system. In PowerCon 2000 - 2000 International Conference on Power System Technology, Proceedings. Vol. 3. Institute of Electrical and Electronics Engineers Inc. 2000. p. 1425-1429. 898178 https://doi.org/10.1109/ICPST.2000.898178
Cha, Jun Min ; Oh, Kwang Hae ; Lee, Byong Jun ; Song, Kil Yeong. / A decision making method for congested transmission lines of KEPCO system. PowerCon 2000 - 2000 International Conference on Power System Technology, Proceedings. Vol. 3 Institute of Electrical and Electronics Engineers Inc., 2000. pp. 1425-1429
@inproceedings{2bf210c6444b460da7eac301bdc47ebf,
title = "A decision making method for congested transmission lines of KEPCO system",
abstract = "In this paper, fuzzy theory is used to quantify some subjective criteria to consider uncertain factors for transmission line reinforcement planning. As it can be easily applied to multi attribute decision making problems such as power system planning, Sugeno's fuzzy integral is also used in the proposed method. To verify the proposed algorithm, some bottle-neck lines are searched for the case that the amount of Maximal Load Supplying Capability(MLSC) is small using the results of contingency analysis for Korea Electric Power Corporation(KEPCO)'s 345 kV transmission line in 1998. And several feasible alternatives are composed for line reinforcement which can solve the bottle-neck problem in KEPCO system.",
keywords = "Decision making, Sugeno's fuzzy integral, Transmission line reinforcement planning",
author = "Cha, {Jun Min} and Oh, {Kwang Hae} and Lee, {Byong Jun} and Song, {Kil Yeong}",
year = "2000",
doi = "10.1109/ICPST.2000.898178",
language = "English",
isbn = "0780363388",
volume = "3",
pages = "1425--1429",
booktitle = "PowerCon 2000 - 2000 International Conference on Power System Technology, Proceedings",
publisher = "Institute of Electrical and Electronics Engineers Inc.",

}

TY - GEN

T1 - A decision making method for congested transmission lines of KEPCO system

AU - Cha, Jun Min

AU - Oh, Kwang Hae

AU - Lee, Byong Jun

AU - Song, Kil Yeong

PY - 2000

Y1 - 2000

N2 - In this paper, fuzzy theory is used to quantify some subjective criteria to consider uncertain factors for transmission line reinforcement planning. As it can be easily applied to multi attribute decision making problems such as power system planning, Sugeno's fuzzy integral is also used in the proposed method. To verify the proposed algorithm, some bottle-neck lines are searched for the case that the amount of Maximal Load Supplying Capability(MLSC) is small using the results of contingency analysis for Korea Electric Power Corporation(KEPCO)'s 345 kV transmission line in 1998. And several feasible alternatives are composed for line reinforcement which can solve the bottle-neck problem in KEPCO system.

AB - In this paper, fuzzy theory is used to quantify some subjective criteria to consider uncertain factors for transmission line reinforcement planning. As it can be easily applied to multi attribute decision making problems such as power system planning, Sugeno's fuzzy integral is also used in the proposed method. To verify the proposed algorithm, some bottle-neck lines are searched for the case that the amount of Maximal Load Supplying Capability(MLSC) is small using the results of contingency analysis for Korea Electric Power Corporation(KEPCO)'s 345 kV transmission line in 1998. And several feasible alternatives are composed for line reinforcement which can solve the bottle-neck problem in KEPCO system.

KW - Decision making

KW - Sugeno's fuzzy integral

KW - Transmission line reinforcement planning

UR - http://www.scopus.com/inward/record.url?scp=84960464320&partnerID=8YFLogxK

UR - http://www.scopus.com/inward/citedby.url?scp=84960464320&partnerID=8YFLogxK

U2 - 10.1109/ICPST.2000.898178

DO - 10.1109/ICPST.2000.898178

M3 - Conference contribution

AN - SCOPUS:84960464320

SN - 0780363388

SN - 9780780363380

VL - 3

SP - 1425

EP - 1429

BT - PowerCon 2000 - 2000 International Conference on Power System Technology, Proceedings

PB - Institute of Electrical and Electronics Engineers Inc.

ER -