Automatic data processing system for integrated cost and schedule control of excavation works in NATM tunnels

Daegu Cho, Hun Hee Cho, Daewon Kim

Research output: Contribution to journalArticle

2 Citations (Scopus)

Abstract

A type-based system is widely used for cost and schedule control in the NATM (New Austrian Tunnelling Method) tunnel. This study raises several limitations of the type-based system: a broad level of control, a distributed approach to cost and schedule data, ad hoc management, and difficulty in deriving meaningful data. Integrated cost and schedule control promises a myriad of benefits on both information flow and construction management. Nevertheless, the integrated approach still seems to be a long way from common use in the construction industry because it requires considerable overhead effort to acquire, track, and analyze the integrated data. The objective of this study is to propose a new method to automate the required processes for implementing cost and schedule integration. We propose an operational-level automatic data processing system for cost and schedule integration. The proposed system consists of a real-time location system for detecting equipment locations, a wireless mesh network for transmitting the location signals to a field office, and a prototype model for transforming the signals to cost and schedule data. Technical feasibility is analyzed through a pilot project. The study offers a new approach to facilitating sensor technologies for cost and schedule integration. © 2014

Original languageEnglish
Pages (from-to)132-141
Number of pages10
JournalJournal of Civil Engineering and Management
Volume20
Issue number1
DOIs
Publication statusPublished - 2014 Jan 1

Fingerprint

Excavation
Tunnels
Costs
Wireless mesh networks (WMN)
Construction industry
Schedule
Integrated
Sensors

Keywords

  • Automation
  • Data integration
  • Information technology
  • NATM
  • RTLS
  • Wireless mesh network

ASJC Scopus subject areas

  • Civil and Structural Engineering
  • Strategy and Management

Cite this

Automatic data processing system for integrated cost and schedule control of excavation works in NATM tunnels. / Cho, Daegu; Cho, Hun Hee; Kim, Daewon.

In: Journal of Civil Engineering and Management, Vol. 20, No. 1, 01.01.2014, p. 132-141.

Research output: Contribution to journalArticle

@article{53661eabc72c4c88abff08a4aadaa78c,
title = "Automatic data processing system for integrated cost and schedule control of excavation works in NATM tunnels",
abstract = "A type-based system is widely used for cost and schedule control in the NATM (New Austrian Tunnelling Method) tunnel. This study raises several limitations of the type-based system: a broad level of control, a distributed approach to cost and schedule data, ad hoc management, and difficulty in deriving meaningful data. Integrated cost and schedule control promises a myriad of benefits on both information flow and construction management. Nevertheless, the integrated approach still seems to be a long way from common use in the construction industry because it requires considerable overhead effort to acquire, track, and analyze the integrated data. The objective of this study is to propose a new method to automate the required processes for implementing cost and schedule integration. We propose an operational-level automatic data processing system for cost and schedule integration. The proposed system consists of a real-time location system for detecting equipment locations, a wireless mesh network for transmitting the location signals to a field office, and a prototype model for transforming the signals to cost and schedule data. Technical feasibility is analyzed through a pilot project. The study offers a new approach to facilitating sensor technologies for cost and schedule integration. {\circledC} 2014",
keywords = "Automation, Data integration, Information technology, NATM, RTLS, Wireless mesh network",
author = "Daegu Cho and Cho, {Hun Hee} and Daewon Kim",
year = "2014",
month = "1",
day = "1",
doi = "10.3846/13923730.2013.801907",
language = "English",
volume = "20",
pages = "132--141",
journal = "Journal of Civil Engineering and Management",
issn = "1392-3730",
publisher = "Vilnius Gediminas Technical University",
number = "1",

}

TY - JOUR

T1 - Automatic data processing system for integrated cost and schedule control of excavation works in NATM tunnels

AU - Cho, Daegu

AU - Cho, Hun Hee

AU - Kim, Daewon

PY - 2014/1/1

Y1 - 2014/1/1

N2 - A type-based system is widely used for cost and schedule control in the NATM (New Austrian Tunnelling Method) tunnel. This study raises several limitations of the type-based system: a broad level of control, a distributed approach to cost and schedule data, ad hoc management, and difficulty in deriving meaningful data. Integrated cost and schedule control promises a myriad of benefits on both information flow and construction management. Nevertheless, the integrated approach still seems to be a long way from common use in the construction industry because it requires considerable overhead effort to acquire, track, and analyze the integrated data. The objective of this study is to propose a new method to automate the required processes for implementing cost and schedule integration. We propose an operational-level automatic data processing system for cost and schedule integration. The proposed system consists of a real-time location system for detecting equipment locations, a wireless mesh network for transmitting the location signals to a field office, and a prototype model for transforming the signals to cost and schedule data. Technical feasibility is analyzed through a pilot project. The study offers a new approach to facilitating sensor technologies for cost and schedule integration. © 2014

AB - A type-based system is widely used for cost and schedule control in the NATM (New Austrian Tunnelling Method) tunnel. This study raises several limitations of the type-based system: a broad level of control, a distributed approach to cost and schedule data, ad hoc management, and difficulty in deriving meaningful data. Integrated cost and schedule control promises a myriad of benefits on both information flow and construction management. Nevertheless, the integrated approach still seems to be a long way from common use in the construction industry because it requires considerable overhead effort to acquire, track, and analyze the integrated data. The objective of this study is to propose a new method to automate the required processes for implementing cost and schedule integration. We propose an operational-level automatic data processing system for cost and schedule integration. The proposed system consists of a real-time location system for detecting equipment locations, a wireless mesh network for transmitting the location signals to a field office, and a prototype model for transforming the signals to cost and schedule data. Technical feasibility is analyzed through a pilot project. The study offers a new approach to facilitating sensor technologies for cost and schedule integration. © 2014

KW - Automation

KW - Data integration

KW - Information technology

KW - NATM

KW - RTLS

KW - Wireless mesh network

UR - http://www.scopus.com/inward/record.url?scp=84896351779&partnerID=8YFLogxK

UR - http://www.scopus.com/inward/citedby.url?scp=84896351779&partnerID=8YFLogxK

U2 - 10.3846/13923730.2013.801907

DO - 10.3846/13923730.2013.801907

M3 - Article

VL - 20

SP - 132

EP - 141

JO - Journal of Civil Engineering and Management

JF - Journal of Civil Engineering and Management

SN - 1392-3730

IS - 1

ER -