Case study of a synchronous hydraulic jack-up system for constructing high-rise residential buildings

Jangwoo Seo, Wi Sung Yoo, Ung Kyun Lee, Chunhak Kim, Kyung In Kang, Hun Hee Cho

Research output: Contribution to journalArticle

4 Citations (Scopus)

Abstract

In recent years, contractors have frequently needed to apply innovative technologies to fulfil architects' creative and intricate designs. They have often encountered abnormal construction conditions. One of the challenging and difficult process is the lifting of a heavy structure called the sky transfer truss (STT), especially if undertaking such a lift is not prevalently experienced. This can result in hazards, accidents, schedule delays, and financial losses to contractors. Traditionally, this structure is fabricated at elevation using scaffolds; however, this approach is costly, time-consuming, and labour- intensive. We introduce a procedure for lifting a 600 metric ton structure that has been fabricated on the ground with a synchronous hydraulic jack-up system. We also discuss the technical difficulties of integrating such a structure into a housing facility. This note addresses several challenging issues: high-accuracy fabrication, design of preventing interference and deformation, and the development of a construction procedure. The case study may be helpful for the flexible construction of extended designs and for the use of a jack-up system in lifting heavy structures of massive sizes and weights.

Original languageEnglish
Pages (from-to)922-926
Number of pages5
JournalCanadian Journal of Civil Engineering
Volume37
Issue number6
DOIs
Publication statusPublished - 2010 Jun 1

Fingerprint

Hydraulic tools
hydraulics
Contractors
Jacks
Scaffolds
accident
Hazards
Accidents
labor
hazard
Personnel
Fabrication
residential building

Keywords

  • Architects' creative designs
  • Heavy structure
  • Synchronous hydraulic jack-up system

ASJC Scopus subject areas

  • Civil and Structural Engineering

Cite this

Case study of a synchronous hydraulic jack-up system for constructing high-rise residential buildings. / Seo, Jangwoo; Yoo, Wi Sung; Lee, Ung Kyun; Kim, Chunhak; Kang, Kyung In; Cho, Hun Hee.

In: Canadian Journal of Civil Engineering, Vol. 37, No. 6, 01.06.2010, p. 922-926.

Research output: Contribution to journalArticle

@article{f700f3aa14074d6b9220121e49606b01,
title = "Case study of a synchronous hydraulic jack-up system for constructing high-rise residential buildings",
abstract = "In recent years, contractors have frequently needed to apply innovative technologies to fulfil architects' creative and intricate designs. They have often encountered abnormal construction conditions. One of the challenging and difficult process is the lifting of a heavy structure called the sky transfer truss (STT), especially if undertaking such a lift is not prevalently experienced. This can result in hazards, accidents, schedule delays, and financial losses to contractors. Traditionally, this structure is fabricated at elevation using scaffolds; however, this approach is costly, time-consuming, and labour- intensive. We introduce a procedure for lifting a 600 metric ton structure that has been fabricated on the ground with a synchronous hydraulic jack-up system. We also discuss the technical difficulties of integrating such a structure into a housing facility. This note addresses several challenging issues: high-accuracy fabrication, design of preventing interference and deformation, and the development of a construction procedure. The case study may be helpful for the flexible construction of extended designs and for the use of a jack-up system in lifting heavy structures of massive sizes and weights.",
keywords = "Architects' creative designs, Heavy structure, Synchronous hydraulic jack-up system",
author = "Jangwoo Seo and Yoo, {Wi Sung} and Lee, {Ung Kyun} and Chunhak Kim and Kang, {Kyung In} and Cho, {Hun Hee}",
year = "2010",
month = "6",
day = "1",
doi = "10.1139/L10-026",
language = "English",
volume = "37",
pages = "922--926",
journal = "Canadian Journal of Civil Engineering",
issn = "0315-1468",
publisher = "National Research Council of Canada",
number = "6",

}

TY - JOUR

T1 - Case study of a synchronous hydraulic jack-up system for constructing high-rise residential buildings

AU - Seo, Jangwoo

AU - Yoo, Wi Sung

AU - Lee, Ung Kyun

AU - Kim, Chunhak

AU - Kang, Kyung In

AU - Cho, Hun Hee

PY - 2010/6/1

Y1 - 2010/6/1

N2 - In recent years, contractors have frequently needed to apply innovative technologies to fulfil architects' creative and intricate designs. They have often encountered abnormal construction conditions. One of the challenging and difficult process is the lifting of a heavy structure called the sky transfer truss (STT), especially if undertaking such a lift is not prevalently experienced. This can result in hazards, accidents, schedule delays, and financial losses to contractors. Traditionally, this structure is fabricated at elevation using scaffolds; however, this approach is costly, time-consuming, and labour- intensive. We introduce a procedure for lifting a 600 metric ton structure that has been fabricated on the ground with a synchronous hydraulic jack-up system. We also discuss the technical difficulties of integrating such a structure into a housing facility. This note addresses several challenging issues: high-accuracy fabrication, design of preventing interference and deformation, and the development of a construction procedure. The case study may be helpful for the flexible construction of extended designs and for the use of a jack-up system in lifting heavy structures of massive sizes and weights.

AB - In recent years, contractors have frequently needed to apply innovative technologies to fulfil architects' creative and intricate designs. They have often encountered abnormal construction conditions. One of the challenging and difficult process is the lifting of a heavy structure called the sky transfer truss (STT), especially if undertaking such a lift is not prevalently experienced. This can result in hazards, accidents, schedule delays, and financial losses to contractors. Traditionally, this structure is fabricated at elevation using scaffolds; however, this approach is costly, time-consuming, and labour- intensive. We introduce a procedure for lifting a 600 metric ton structure that has been fabricated on the ground with a synchronous hydraulic jack-up system. We also discuss the technical difficulties of integrating such a structure into a housing facility. This note addresses several challenging issues: high-accuracy fabrication, design of preventing interference and deformation, and the development of a construction procedure. The case study may be helpful for the flexible construction of extended designs and for the use of a jack-up system in lifting heavy structures of massive sizes and weights.

KW - Architects' creative designs

KW - Heavy structure

KW - Synchronous hydraulic jack-up system

UR - http://www.scopus.com/inward/record.url?scp=77953759188&partnerID=8YFLogxK

UR - http://www.scopus.com/inward/citedby.url?scp=77953759188&partnerID=8YFLogxK

U2 - 10.1139/L10-026

DO - 10.1139/L10-026

M3 - Article

AN - SCOPUS:77953759188

VL - 37

SP - 922

EP - 926

JO - Canadian Journal of Civil Engineering

JF - Canadian Journal of Civil Engineering

SN - 0315-1468

IS - 6

ER -